The City of Washington, Indiana

Small City... Big Possibilities

Business 50 West - Overall Project Progress

Business 50 West Project Progress Update #47

 

 

Currently Phase I of Business 50 West is being constructed.  It is anticipated that all major work on Phase I will be completed this week.  At the end of last week, approximately 97% of the Road Project, 100% of Water and 100% of the Sanitary Project have been completed.  At this time 100% of curb, sidewalks, driveways, lighting, asphalt paving, sod and seeding have been completed.  Pavement markings and completion of the traffic signals will be completed shortly.  Although the project is coming to an end, there is still some work to be done.  Please slow down and be aware of lance changes, flaggers and trucks entering and exiting the work zone.