Business 50 West - Overall Project Progress

Bus. 50 West Project Progress Update #26

 

Currently Phase I of Business 50 West is being constructed.  It is anticipated that Phase I will be completed early 2021, weather pending.  At the end of last week, approximately 40% of the road project, 93% of sewer, and 94% of the water project have been completed.  Upon the completion of the underground utility work, surface work will begin.  At this time 55% of curb, 16% of sidewalk and 32% of driveways are completed.  Other work items such as lighting, traffic signals, signing, etc. will be completed intermittently throughout the project.  Asphalt paving will be completed at the end of the project (Spring 2021) once all other elements are in-place.