Business 50 West - Overall Project Progress
Business 50 West - Overall Project Progress Update #31
Currently Phase I of Business 50 West is being constructed. It is anticipated that Phase I will be completed in early 2021, weather pending. At the end of last week, approximately 45% of the Road project, 94% of Water, and 96% of sewer project have been completed. Upon the completion of underground utility work, surface work will begin. At this time 56% of curb, 24% of sidewalks and 32% of driveways are completed. Other work items such as lighting, 50% complete, traffic signals, signing, etc. will be completed intermittently throughout the project. Asphalt paving will be completed at the end of the project (Spring 2021) once all other elements are in-place.