The City of Washington, Indiana

Small City... Big Possibilities

Business 50 West - Overall Project Progress

Business 50 West - Overall Project Progress Update #14

 

Currently Phase I of Business 50 West is being constructed.  It is anticipated that Phase I will be completed in late 2020/early 2021, weather pending.  At the end of last week, approximately 87% of water project,  67% of sewer project and 27% of roadway is completed.  Upon completion of the underground utility work, surface work will begin.  At this time 0% of curb, sidewalk and driveways are completed.  Other work items such as lighting, traffic signals, signage, etc. will be completed intermittently throughout the project.  Asphalt paving will be completed at the end of the project (spring 2021) once all other elements are in-place.